Interior Our Work Order

  1. Select order of operations as based on clients living needs

  2. Move agreed upon furniture as needed

  3. Protect and cover flooring and furniture as needed (plastic and rosin paper)

  4. Remove switch plates

  5. Patch all drywall and window sills

  6. Remove, and/or drop down light fixtures as necessary or cover

  7. Caulk all seams transitioning from walls to ceiling/ baseboards to ensure clean lines

  8. Prime all repairs and raw materials (drywall primer for walls/ceilings, and epoxy, shellac, or oil for wood surfaces depending on application)

  9. Previously oil painted surfaces need sanding, and oil priming before paint application

  10. Medium to drastic color changes need drywall priming and two full coats to prevent shadowing

  11. Paint Order: Ceilings, closets, doors/trim/baseboards, walls

  12. Remove plastics,rosin paper, and tape

  13. Touch-ups and switch plate installation

  14. Vacuum leftover debris as needed

  15. Rock and Roll Painting crew job walk

  16. Rock and Roll Painting and client job walk